February 24, 2017LOUGHER VIADUCT – SOUTH WALES
February 24, 2017Working in one of the busiest stations in the UK, it’s the gateway to London, over a 2 year period with a mixture of possession and non possession working. 140 tonnes timber crane in for track protection. 1296 man hours for the Easter blockade. 100, 40 yard skips came out, 1200 tonnes craned out, 140 tonnes of timber matting craned in for track protection. 500 ton crane use to lift in and out all equipment and debris. 6-12 hours shifts for the Easter blockade.